Tenders invited for Extension Works to Lung Fu Road, Tuen Mun
*************************************************************
The works are scheduled to commence in January 2027 and will take about 48 months to complete. The works mainly include:
- construction of an elevated carriageway and an at-grade carriageway of approximately 600 meters in length connecting Lung Fu Road to Tsing Wun Road northbound;
- construction of an elevated carriageway and an at-grade carriageway of approximately 800 meters in length connecting Tsing Wun Road to Lung Fu Road southbound;
- reconstruction of an elevated carriageway and an at-grade carriageway of approximately 400 meters in length connecting Tsing Wun Road southbound to Wong Chu Road eastbound;
- design, supply and installation of Fully Variable Message Sign (FVMS) at Tuen Mun Road southbound near MTR Siu Hong Station; and
- carrying out associated works including noise barriers, geotechnical works, electrical and mechanical works, drainage works, waterworks, street lighting works, traffic facilities, landscaping works and environmental mitigation measures.
The HyD has commissioned WSP (Asia) Limited as the consultant to design and supervise the construction works. Interested tenderers must download the tender forms and other particulars from the Electronic Tendering System for works contracts (e-TS(WC)).
The invitation to tender was gazetted today. Tenderers shall submit completed tenders in electronic format via e-TS(WC). Submission of tenders will close at noon on July 31, 2026 (Friday).
For enquiries, please contact WSP (Asia) Limited at 2217 2227.
Ends/Friday, June 5, 2026
Issued at HKT 9:00
Issued at HKT 9:00
NNNN