LCQ22: Defaulted works carried out by Buildings Department
**********************************************************
Following is a question by the Hon Andrew Lam and a written reply by the Secretary for Development, Ms Bernadette Linn, in the Legislative Council today (November 18):
Question:
Provisions such as sections 26 (Dangerous buildings), 26A (Defective buildings), 28 (Drainage) and 30B (Obligation on owners to carry out prescribed inspection and prescribed repair in respect of buildings) of the Buildings Ordinance (Cap. 123) stipulate that where buildings are dangerous or out of repair and the owners have failed to comply with a statutory order within the specified time, the Building Authority (i.e. the Director of Buildings) may arrange for government contractors to carry out the defaulted works and then recover the cost of these works, together with supervision charges, from the owners under section 33 of the Ordinance. In this connection, will the Government inform this Council:
(1) of the number of cases in which the Buildings Department exercised its power under the Buildings Ordinance (Cap. 123) to carry out defaulted works in each of the past five years, with a breakdown by (i) reason (e.g. owners failing to comply with orders upon the expiry of the time limit, emergency situations posing imminent danger, owners being unable or refusing to organise the works, etc.) and (ii) type of works (e.g. repair of spalling on external walls/structural elements, repair of common drainage, clearance of dangerous buildings/unauthorised building works, mandatory building inspection/window inspection);
(2) of the specific administrative procedures currently in place for handling defaulted works (including the procedures, timeline and time required from the initiation of action to recovery of sums);
(3) of the total amount involved in defaulted works in each of the past five years; and the number of cases in which the amounts (including the actual cost of the works, additional supervision charges and interest) have been successfully recovered, the amount involved and its percentage in the total receivable amount; and
(4) of the number of cases of defaulted works for which the amounts have not yet been recovered or are overdue to date, the amount involved, the longest period of default, and the number of buildings among them on which an encumbrance has been imposed?
Reply:
President,
In respect of dilapidated or dangerous buildings and defective drainage systems, the Buildings Department (BD) takes enforcement action under the Buildings Ordinance (Cap. 123) (BO), including issuing investigation orders/repair orders/removal orders to owners. In addition, under the Mandatory Building Inspection Scheme (MBIS), the BD also issues MBIS notices on a risk-based approach, requiring owners/owners' corporations to carry out prescribed inspection and repair. If an owner fails to comply with a statutory order/notice without reasonable excuse, the BD will consider instituting prosecution against the owner concerned. In case of emergency or under special circumstances (such as where the owner has deceased, cannot be located, is an elderly, or in the case of "three-nil" buildings, etc), the BD will carry out default works on behalf of the defaulting owners for higher-risk and long-overdue statutory orders/notices, and subsequently recover the cost of works from the owners, together with a supervision charge and a surcharge. Where emergency works are involved, the owners are only required to pay the cost of works and the supervision charge, and the BD will not impose any surcharge.
A reply to the various parts of the question is as follows:
(1) Over the past five years, the annual breakdown of the number and classification of default works carried out by the BD is set out at Annex 1.
(2) When it is decided to carry out default works on behalf of the defaulting owner(s), the BD will first appoint a consultancy firm and a registered contractor to carry out the necessary investigation/inspection and works, and upon completion of the works, recover the cost of works, supervision charge, and (where applicable) surcharge from the owner(s). After the BD issues a demand note, the owner(s) must settle the amount due within 14 days from the date of issue of the demand note. If the owner(s) fails to make payment on time, the BD will serve a certificate of arrears for registration in the Land Registry, constituting a first charge on the premises to safeguard the Government's interest, and interest at the rate of 10 per cent per annum will be charged on the unpaid amount. If the owner(s) still fails to settle the payment within one month after the registration of the certificate of arrears, the BD will refer the case to the Department of Justice for taking legal action to recover the debt through civil proceedings.
The time required for carrying out default works is affected by various factors, such as the nature, scale, and complexity of the removal/repair/investigation works, whether the owner(s) or occupier(s) concerned are co-operative, and whether any genuine hardship is encountered in carrying out the works. In general, the removal of minor unauthorised building works (UBWs), localised repairs to defective building elements or drainage pipes, and emergency works for removing loose building elements can be completed within one to several days. As for other cases, such as those involving larger-scale repairs, removal of large-scale rooftop UBWs, or arrangements for the decanting/vacating of occupiers, a longer time is required, generally taking from several months to a year and a half from commencement to completion. A small number of complex cases, such as those involving detailed investigation or co-ordination among multiple owners, may take an even longer time.
(3) Over the past five years, the annual breakdown of the number of demand notes issued by the BD following the carrying out of default works or emergency works pursuant to the statutory orders/notices mentioned above, the amounts involved, and the amounts successfully recovered are set out at Annex 2.
(4) As at September 30, 2026, the BD carried out about 2 500 default or emergency works cases over the past five years, of which the default works costs of about 800 cases had not yet been fully settled, involving about $53 million. The BD has registered the certificates of arrears against the units concerned in the Land Registry as a first charge. The BD does not maintain readily available statistics on the period in arrears.
Ends/Wednesday, November 18, 2026
Issued at HKT 15:20