LCQ20: Transformation of public play spaces
*******************************************
     Following is a question by Dr the Hon Elvin Lee and a written reply by the Secretary for Culture, Sports and Tourism, Miss Rosanna Law, in the Legislative Council today (November 18):

Question:

     There are views that high-quality public play facilities are crucial for children's physical and mental development and are essential for creating liveable communities and supporting the Government's policy of encouraging childbirth. As early as the 2019 Policy Address, the Government announced the launch of a five-year plan of public play spaces (PPS) transformation (the Plan), which was originally intended to transform more than 170 public playgrounds for children managed by the Leisure and Cultural Services Department (LCSD) within five years. However, to date, only 18 venues have completed the transformation works and been opened for public use. According to the information provided by LCSD in its reply to this Council regarding the 2026-2027 Estimates of Expenditure, each PPS transformation project normally takes three to five years to proceed from the stage of preliminary planning and community participation to completion, representing a significant shortfall compared to the target set in the Policy Address at the time. As funding for the relevant works has already been approved, the community is eagerly looking forward to the authorities expediting the transformation of PPSs. In this connection, will the Government inform this Council:

(1) as it is learnt that the reasons why the transformation works take a relatively long time include the complexity of the works procedures, the time required for interdepartmental coordination and the lengthy design and district consultation processes, whether the authorities have further reviewed, among the various stages in project planning and construction, which parts require the longest time and have become bottlenecks; if so, of the details, if not, the reasons for that;

(2) whether, in light of the bottlenecks referred to in (1), the authorities have formulated specific enhancement measures, particularly the reallocation of resources or the streamlining of procedures, to effectively expedite the implementation of the remaining projects; if so, of the details, if not, the reasons for that; and

(3) in order to expedite the implementation of the remaining projects, whether the authorities will set out clear new time targets for the overall progress of the Plan; if so, of the specific time targets; if not, the reasons for that?

Reply:

President,

     My reply to the questions raised by Dr the Hon Elvin Lee is as follows:

(1) In the 2019 Policy Address, the Government announced its plan to modify more than 170 public play spaces (PPSs) managed by the Leisure and Cultural Services Department (LCSD) across the territory over the following five years. The plan encourages and promotes community participation and public engagement in the process of modifying these facilities, making them more innovative and fun while meeting the needs of residents.

     To take the plan forward, the LCSD has announced a list of the PPSs to be modified and drawn up works schedules and arrangements. As modifying all PPSs at the same time would substantially reduce the facilities available for public use during the works periods and cause considerable inconvenience to the public, the LCSD is implementing the plan in phases to better address the actual needs of the public. The LCSD and the Architectural Services Department (ArchSD) have scheduled the projects according to their urgency and priority. One important consideration is to avoid, as far as possible, launching multiple projects concurrently within the same district, ensuring that sufficient children's play facilities remain available in each district during the works period. Phased implementation also enables various departments to draw on the experience gained from completed projects, continuously refine the work processes and consultation arrangements, and make appropriate adjustments to subsequent projects. In this way, the modified PPSs will be innovative and fun while meeting the needs of residents.

     The LCSD has consulted the respective District Councils on site selection. The projects are at various stages of progress - 19 have been completed and opened for public use; 10 are under construction; and five and 25 are scheduled to commence in 2026-27 and 2027-28 respectively. The remaining projects are at various planning stages, their commencement and anticipated completion dates will be announced in due course.

     Unlike regular playground refurbishment projects, the LCSD has, through workshops, questionnaires and other means, widely consulted local communities and other stakeholders, including representatives of children's organisations, and incorporated feasible suggestions into the designs. Each project also makes good use of the site's terrain, integrates natural elements and adopts more tailor-made play equipment with a view to creating distinctive features for each PPS. In fact, the transformed PPSs have been well received by the public. For instance, Sham Shui Po Park is a major project that adopts "nature" as its design theme in response to public views, with "water", "sand" and "plants" as its principal design elements. It also features the tallest and longest slide among all the LCSD playgrounds. Besides, local characteristics are likewise reflected in the design of a transformed PPS. For example, Che Kung Miu Road Playground takes "wind spinner" as its design theme and features a distinctive and challenging windmill adventure play tower, highlighting the district's characteristics while enhancing the appeal of the facilities.

     The modification projects also require substantial preliminary preparation, design and co-ordination. The design team has to work with the awarded contractor on the detailed design, including adjusting facilities to suit site conditions and terrain, selecting materials and colours, and undertaking structural design, mould fabrication, factory production, safety certification, as well as post-installation inspection and accreditation. These processes generally take an additional six months to one year to ensure that the facilities comply with recognised international design guidelines and safety standards. The actual time required for each project will be subject to its design, scale and complexity.

     The construction period for a modification project also depends on whether phased site enclosure is necessary, having regard to actual circumstances, in order to safeguard public safety and minimise the impact of the works on nearby facilities, residents and communities. In addition, the progress may also be affected by unforeseeable circumstances, such as frequent or prolonged adverse weather and the discovery of underground utilities, tree roots or unfavourable ground conditions during construction, etc.

(2) and (3) As stated in part (1) of this reply, the modification of PPSs involves multiple rounds of community consultation. Designs are repeatedly adjusted and refined in response to views from the public and other stakeholders so as to meet the actual needs of users. These consultation and design refinement processes are essential to taking the plan forward, and it takes time to complete. While implementing the plan in phases, the LCSD and the ArchSD have adopted a number of measures to enhance the efficiency of the various processes, including conducting joint community participation activities for multiple projects; making reference to the views and suggestions gathered from previous modification projects when commencing preliminary designs; shortening the lead time required for technical studies and detailed design; undertaking projects through term contracts; and streamlining construction procedures, etc. These measures help taking forward the projects effectively while ensuring the quality and safety of the works.

     The LCSD and the ArchSD will continue to monitor the progress of each project and deploy resources flexibly in light of actual circumstances. They will proceed with the remaining projects in an orderly manner in accordance with the principle of phased implementation, so that the public can enjoy PPSs that are innovative and interesting.
 
Ends/Wednesday, November 18, 2026