CoI into Diaphragm Wall and Platform Slab Construction Works at Hung Hom Station Extension under Shatin to Central Link Project to resume substantive hearing on January 28
***************************************************************

The following is issued on behalf of the Commission of Inquiry into the Diaphragm Wall and Platform Slab Construction Works at the Hung Hom Station Extension under the Shatin to Central Link Project:

     The Commission of Inquiry into the Diaphragm Wall and Platform Slab Construction Works at the Hung Hom Station Extension under the Shatin to Central Link Project directs that the substantive hearing to hear closing addresses by Counsel for the Commission and the involved parties shall commence at 9.30am on January 28 at the hearing room on the first floor of the former Tsuen Wan Law Courts Building, 70 Tai Ho Road, Tsuen Wan, New Territories, Hong Kong.
 

Ends/Friday, January 25, 2019