| A/H17/127 |
| Shouson Hill & Repulse Bay |
| Hong Kong District |
| 30/09/2011 |
| 23 South Bay Close, Repulse Bay, Hong Kong |
| Proposed Flat (Staff Quarters) |
Newspaper Notice 
Gist 
|
| 48 |
| Nature |
Clarification on the drainage proposal. |
| Decision |
Accepted and Exempted from Publication |
|
| Nature |
The applicant provided further information which includes revised development parameters (including reduction in the number of staff quarter units and overall building height from 121.45mPD to 114.95mPD), a revised landscape master plan, a revised traffic impact assessment, a revised drainage and sewerage impact assessment and responses to departmental comments. |
| Decision |
Accepted but Not Exempted from Publication
Newspaper Notice
|
| No. of Comments on Further Information Already Received |
91 |
|
| Nature |
The applicant provided further information which includes revised development parameters (including reduction in the overall building height from 114.95mPD to 111.95mPD), section plans and perspectives and responses to departmental comments. |
| Decision |
Accepted and Exempted from Publication |
|
| Nature |
The applicant provided further information which includes revised development parameters, landscape plans and perspectives and responses to departmental comments. |
| Decision |
Accepted and Exempted from Publication |
|
| Nature |
The applicant clarifies on the site formation level and GFA concession. |
| Decision |
Accepted and Exempted from Publication |
|
| Nature |
The applicant clarifies on the building height of the existing school building and and responses to departmental comments. |
| Decision |
Accepted and Exempted from Publication |
|
| 20/04/2012 |
| - |