| Independent
Assessment of Year 2000 Preparations of Hong Kong Incorporated Authorised
Institutions Standard Terms of Reference ("STOR")
Introduction
| 1. |
The name
of Hong Kong incorporated AI ] is requested by the Hong Kong Monetary
Authority ("HKMA") to engage a Reviewer to conduct an
independent assessment of the Year 2000 preparations of the institution
and produce a report on the matters specified in paragraphs 4 and
5 below. |
Deadlines established by the HKMA
| 2. |
The HKMA has established 31 December
1998 as the deadline by which all authorized institutions ("AIs")
are expected to be Year 2000 compliant in accordance with the following
definition:
"A Year 2000 compliant system should perform,
function and manage data involving dates without being abnormally
affected by dates spanning the period prior to, during and
after the Year 2000."
Therefore, all AIs are expected by 31 December
1998 to have:
|
| i. |
completed the modification and
testing of individual systems; and
|
| ii. |
tested the interaction of modified
systems with the institution's other systems with which they
interface directly.
|
|
| 3. |
The HKMA has also established 31 March
1999 as the date by which all AIs should have largely finalised
and completed testing of contingency plans, though it may be necessary
to update and test their plans after that date to take account of
changing circumstances. |
Scope of assessment
| 4. |
The Reviewer should report on whether
the local management of the institution has taken or is taking the
necessary measures to resolve the Year 2000 problem of the systems,
especially the critical systems, that would be used spanning the
period prior to, during and after the Year 2000 by the institution
and its local and overseas subsidiaries and branches (if any). If
the institution is part of a larger banking group, the Reviewer
should take into account the extent to which its Year 2000 project
is being directed by the parent bank in assessing the efforts of
the local management. The Reviewer should also check, through discussion
with the local management and through examination of any relevant
documentary evidence, whether the necessary steps are being taken
by the parent bank to resolve the Year 2000 problem in respect of
the Hong Kong incorporated institution and its subsidiaries and
branches.
|
| 5. |
In particular, the Reviewer should report
on:
| i. |
whether the senior management of
the institution has been giving sufficient priority to, and
maintaining adequate oversight of, the Year 2000 problem of
the institution and its subsidiaries and branches;
|
| ii. |
whether the institution has taken
the necessary measures to promote the awareness of the Year
2000 problem within the institution including its subsidiaries
and branches;
|
| iii. |
whether the institution has taken
the necessary measures to assess the impact of the Year 2000
problem on the institution and its subsidiaries and branches,
to formulate a sound and effective project plan to address
the Year 2000 problem and to ensure that sufficient resources
have been allocated to the project;
|
| iv. |
whether the institution has taken
the necessary measures to ensure the systems that would be
used by the institution and its subsidiaries and branches,
especially critical systems, have been or would be properly
modified;
|
| v. |
whether the institution has taken
the necessary measures to ensure the systems that would be
used by the institution and its subsidiaries and branches,
especially critical systems, have been or would be properly
tested for Year 2000 readiness;
|
| vi. |
whether the institution has taken
the necessary measures to ensure the systems that would be
used by the institution and its subsidiaries and branches,
especially critical systems, have been or would be properly
implemented in production;
|
| vii. |
whether the institution has taken
the necessary measures to ensure contingency plans have been
or would be properly developed and tested to ensure business
continuity of the institution and its subsidiaries and branches
and to deal with other Year 2000 problems that may arise;
|
| viii. |
whether the institution has taken
the necessary measures to ensure the Year 2000 issue-related
risks arising from its business counterparties have been or
would be properly assessed and managed;
|
| ix. |
whether the progress of Year 2000
preparations of the institution and its subsidiaries and branches
is behind, ahead or on schedule according to the project plan;
|
| x. |
whether he has identified any major
concerns or weaknesses in the institution's Year 2000 preparations
in the course of the assessment, including those which might
affect the ability of the institution to meet the deadlines
established by the HKMA as specified in paragraphs 2 and 3;
and (xi) any recommendations on additional actions that may
assist the senior management of the institution to address
the problem areas.
|
|
| 6. |
It is understood that the responsibility
for addressing the institution's Year 2000 issues rests with management
of the institution. It is also understood that the Reviewer is unable
to provide:
| i. |
any guarantee that the institution
including its subsidiaries and branches will have no problems
arising from Year 2000 issues;
|
| ii. |
any acceptance of responsibility
for managing the Year 2000 project and the project risk;
|
| iii. |
any certification of Year 2000
compliance;
|
| iv. |
any guarantee that all the weaknesses
in the Year 2000 preparations of the institution including
its subsidiaries and branches will be identified; and
|
| v. |
any guarantee that the implementation
of any recommendations made by the Reviewer will necessarily
result in the institution becoming Year 2000 compliant or
that the recommendations will necessarily address all the
issues which the institution including its subsidiaries and
branches may face in dealing with the Year 2000 issues. |
|
Guidance for conducting independent assessment
| 7. |
For the purpose of this independent assessment,
the HKMA has devised a Guidance Note on the Independent Assessment
of Year 2000 Preparations of a Hong Kong Incorporated Authorized
Institution (the "Guidance Note") (see Annex
A-1) to provide practical guidance to the Reviewer
in conducting the assessment. The Reviewer might wish to submit
the Guidance Note to the institution in advance so that the latter
can provide written responses to main areas identified in the Guidance
Note and provide relevant documentary evidence to the Reviewer for
review prior to the assessment. |
Time Frame for the Report
| 8. |
The Reviewer should submit the report
including any checklist completed for the institution by [ 5 October
1998 ] to the institution, which should then forward the same to
the HKMA, together with management's comments on the report no later
than [ 19 October 1998 ]. |
Annex A-1
Guidance Note on Independent Assessment of Year 2000 Preparations
of a Hong Kong Incorporated Authorised Institution
Introduction
This guidance note aims to provide some practical guidance to a Reviewer
for conducting an independent assessment of the Year 2000 preparations
of a Hong Kong incorporated authorized institution ("AI").
The main objective of the Reviewer is to assess whether the local
management of the institution has taken or is taking the necessary
measures to resolve the Year 2000 problem of the systems, particularly
the critical systems, that would be used spanning the period
prior to, during and after the Year 2000 by the institution and its
local and overseas subsidiaries and branches. If the institution
is part of a larger banking group, the Reviewer should take into account
the extent to which its Year 2000 project is being directed by the parent
bank in assessing the efforts of the local management. Where it is the
case, the Reviewer should check, through discussion with the local management,
whether the necessary steps are being taken by the parent bank to resolve
the Year 2000 problem in respect of the Hong Kong incorporated institution
and its subsidiaries and branches.
This guidance note contains eight sections, each of which provides
a general description of the sound practices related to the various
important aspects of the Year 2000 compliance work. It also includes
a list of suggested questions which the Reviewer may ask pertaining
to each important aspect of the Year 2000 compliance work. It should
be noted that the questions suggested are not meant to be exhaustive.
The Reviewer can ask additional questions and where appropriate obtain
documentary evidence from the institution to ascertain the claims and
responses made by the institution. For this particular purpose, the
guidance note has also included suggested documentary evidence that
the Reviewer can ask for review of the matters under each section.
Section I - Establishing Strategic Objective And Management Oversight
Objective of assessment:
The Reviewer should assess and report on whether the senior management
of the institution has been giving sufficient priority to, and maintaining
adequate oversight of, the Year 2000 problem of the institution and
its subsidiaries and branches.
General description of sound practices:
The institution should establish the resolution of the Year 2000 problem
as a strategic objective of the institution including all its subsidiaries
and branches. The Year 2000 problem should be taken into account when
considering other strategic business initiatives (e.g., mergers, acquisitions,
major system development, corporate alliances, or business expansions).
Regarding the management oversight of the Year 2000 problem, there
should be a clear assignment of lines of responsibility and accountability.
In particular, a senior executive should be assigned with explicit oversight
responsibility and accountability for the overall Year 2000 preparation
efforts of the institution and its subsidiaries and branches. The institution
should also establish its Year 2000 project team (comprising the appropriate
officers from various departments) to co-ordinate the Year 2000 readiness
work of the institution as a whole including its subsidiaries and branches.
It would also be useful to set up a Year 2000 project steering committee
involving senior executives from relevant departments to provide steers
to the Year 2000 project team. In addition, the institutions board
of directors and senior management should be kept informed through regular
reports on the status of Year 2000 preparations of the institution and
its subsidiaries and branches.
There should also be explicit and proactive involvement of the internal
audit, or possibly external audit, in monitoring the Year 2000 progress
of the institution and its subsidiaries and branches. Exceptions identified
should be followed-up promptly.
Suggested questions that the Reviewer may ask:
| 1. |
Have the senior management and board
of directors clearly established the resolution of the Year 2000
issue as a strategic objective?
|
| 2. |
Has the institution taken Year 2000 into
account when considering other strategic business initiatives (e.g.,
mergers, acquisitions, major system development, corporate alliances,
or business expansions)? What due diligence and other measures would
be taken in merger and acquisition transactions to protect against
inheriting Year 2000 problems?
|
| 3. |
Has the institution clearly assigned
the responsibilities for dealing with various aspects (technical,
operational, business line) of the Year 2000 preparations?
|
| 4. |
Has a senior executive been assigned
with explicit oversight responsibility and accountability for the
overall Year 2000 preparation efforts of the institution and its
subsidiaries and branches?
|
| 5. |
Has the institution established its Year
2000 project team (including the appropriate officers from various
departments) to co-ordinate the preparations of the institution
as a whole and its subsidiaries and branches?
|
| 6. |
Has a Year 2000 project steering committee
been set up involving senior executives from relevant departments
to provide policy steers to the Year 2000 project team?
|
| 7. |
Have the institution's board of directors
and senior management been receiving regular reports, at least on
a monthly basis, on the status of Year 2000 preparations of the
institution and its subsidiaries and branches?
|
| 8. |
Has there been explicit and proactive
involvement of the internal audit, or external audit, in regular
monitoring of the Year 2000 progress of the institution and its
subsidiaries and branches?
|
| 9. |
Does internal and/or external audit communicate
the exceptions identified and findings to the senior management
and even board of directors? Has the institution in general made
timely follow-up actions in response to the findings? |
Suggested documentary evidence that the Reviewer can ask for review:
- Relevant board minutes and memos from senior management, minutes
of Year 2000 project steering committee and project team, copies of
management status reports on Year 2000 project of the institution;
- Correspondence with subsidiaries/branches/head office (if any);
and
- Sample of audit plan of internal auditors, or external auditors,
and findings and follow-up actions of the institution.
Section II - Organisational Awareness
Objective of assessment:
The Reviewer should assess and report on whether the institution has
taken the necessary measures to promote the awareness of the Year 2000
problem within the institution including its subsidiaries and branches.
General description of sound practices:
The board of directors and senior management should have a clear understanding
of the Year 2000 problem that it is a business survival issue and not
just a technical issue. Directors and senior management should understand
their fiduciary duties to ensure necessary measures would be taken to
prepare for the Year 2000 problem. Senior management should communicate
to the staff (including line management, technical staff, end users
of systems, credit officers) of the institution and its subsidiaries
and branches about the strategic implications of the Year 2000 problem,
particularly the strategic objective to resolve the Year 2000 problem.
The staff (including line management, technical staff, end users of
systems, credit officers) of the institution and its subsidiaries and
branches must also realise how the millennium change may affect their
activities. They should also understand that their activities depend
on numerous other parties (for example, customers, correspondents, and
service providers) that must also be ready for the millennium change.
The institution and its subsidiaries and branches must be aware of
the various supervisory requirements for Year 2000 preparedness established
in each of the jurisdictions in which they operate.
Suggested questions that the Reviewer may ask:
| 1. |
Do the board of directors and senior
management have a clear understanding of the Year 2000 problem,
that it is a business survival issue and not just a technical issue?
|
| 2. |
Do the directors and senior management
understand their fiduciary duties to ensure necessary measures would
be taken to prepare for the Year 2000 problem?
|
| 3. |
Has the senior management communicated
to the staff (including line management, technical staff, end users
of systems, credit officers) of the institution and its subsidiaries
and branches about the strategic implications of the Year 2000 problem,
particularly the strategic objective to resolve the Year 2000 problem?
|
| 4. |
Do the staff (including line management,
technical staff, end users of systems, credit officers) of the institution
and its subsidiaries and branches realise how the millennium change
may affect the their activities? Do they understand that their activities
would depend on numerous other parties (for example, customers,
correspondents, and service providers) that must also be ready for
the millennium change?
|
| 5. |
Are the institution and its subsidiaries
and branches aware of relevant supervisory benchmarks, target dates,
and other sound practices identified for Year 2000 compliance in
each jurisdiction in which they operate? Do they understand the
regulatory consequences of failures in preparing for the Year 2000
issues? If certain systems would be provided by the parent bank
(if any), has the institution informed its parent bank about the
local regulatory requirements so that the parent bank will take
into account such requirements in modifying and testing the systems? |
Suggested documentary evidence that the Reviewer can ask for review:
- Sample of internal awareness programme, training materials,
circulars/ correspondents; and
- Correspondence with customers.
Section III - Assessment and detailed planning
Objective of assessment:
The Reviewer should assess and report on whether the institution has
taken the necessary measures to assess the impact of the Year 2000 problem
on the institution and its subsidiaries and branches, to formulate a
sound and effective project plan to address the Year 2000 problem and
to ensure that sufficient budget and resources have been allocated to
the project.
General description of sound practices:
The institution must determine the size and complexity of the Year
2000 problem by developing detailed inventory of the systems that it
would use, regardless of whether the systems are in-house developed
or provided by the parent bank (if any), vendors or service providers
(e.g., exchanges, clearing houses). The inventory should include centralised
or decentralised computer hardware, software, networks, or equipment
with embedded computer chips, and system interfaces. Equipment with
embedded computer chips include security systems, vaults, telephones,
faxes, heating/cooling systems, entrance systems, fire alarm, safe deposit
box systems, network equipment, building services, escalators, elevators,
air-conditioning systems, audio response systems, tape recording systems
and dealing systems. The detailed inventory should identify which systems
would be affected if the Year 2000 problem of the systems was not resolved
and the risk analysis. Priority should be set on each system according
to the risks assessed.
The institution should contact those vendors and service providers
as to their progress and plans for addressing the year 2000 issue. The
development of effective communication channels with vendors and service
providers is essential. Contracts may need to be reviewed and amended,
as appropriate. Current and future purchases of hardware/software technology
should require certification that it is Year 2000 compliant. If contract
changes or modifications are refused, then the institution should consider
replacing the service or product.
The institution should develop a detailed project plan to detail what
and how much efforts are necessary to address the Year 2000 problem
of the institution and its subsidiaries and branches. The project plan
should include breakdown of the project into manageable tasks with a
concrete timetable for meeting each milestone. It should also establish
trigger dates for making decisions on adopting alternatives should there
be slippage on major dependencies on external factors.
The project plan should outline which systems will be modified and
what the testing and implementation process will entail. It should recognise
that testing will be the single most important resource intensive part
of the project. The resource needs should be identified and secured,
including appropriately skilled personnel, contractors, vendor support,
budget allocations, and hardware capacity. Responsibilities and accountabilities
need to be clearly defined and agreed upon for each step in the project
plan.
Procedures for monitoring the progress against schedules and the utilised
resources against budget should be devised with appropriate information
flowing to the senior management and board of directors on a regular
basis.
Suggested questions that the Reviewer may ask:
| 1. |
Has the institution determined the size
and complexity of the Year 2000 problem by developing detailed inventory
of the systems that it would use, regardless of whether the systems
are in-house developed or provided by the parent bank (if any),
vendors or service providers (e.g., exchanges, clearing houses)?
|
| 2. |
Does the inventory include centralised
or decentralised computer hardware, software, networks, and system
interfaces? Does the inventory include equipment with embedded computer
chips such as security systems, vaults, telephones, faxes, heating/cooling
systems, entrance systems, fire alarm, safe deposit box systems,
network equipment, building services, escalators, elevators, air-conditioning
systems, audio response systems, tape recording systems and dealing
systems?
|
| 3. |
Does the detailed inventory identify
which systems would be affected if the Year 2000 problem of the
systems was not resolved and the risk analysis? Has priority been
placed on each system according to the risks assessed?
|
| 4. |
Has the institution contacted those vendors
and service providers as to their progress and plans for addressing
the year 2000 issue? Have effective communication channels with
vendors and service providers been developed?
|
| 5. |
Have contracts and insurance policies
been reviewed and amended, as appropriate? Do current and future
purchases of hardware/software technology require certification
that it is Year 2000 compliant? If contract changes or modifications
are refused, would the institution and its subsidiaries and branches
consider replacing the service or product?
|
| 6. |
Has the institution developed a detailed
project plan to detail what and how much efforts are necessary to
address the Year 2000 problem of the institution and its subsidiaries
and branches? Does the project plan include breakdown of the project
into manageable tasks with a concrete timetable for meeting each
milestone? Have responsibilities and accountabilities been clearly
defined and agreed upon for each step in the project plan? Does
the project plan establish trigger dates for making decisions on
adopting alternatives for major dependencies on external factors
(e.g., delivery of Year 2000 compliant systems by vendors or service
providers)?
|
| 7. |
Does the project plan outline which systems
should be replaced, upgraded or otherwise modified and what the
modification, testing and implementation process will entail? Does
the project plan recognise that testing will be the single most
important resource intensive part of the project (around 50 to 60%
of the total time, funding, and personnel needed)?
|
| 8. |
Have the resource needs been identified
and secured, including appropriately skilled personnel, contractors,
vendor support, budget allocations, and hardware capacity? Has a
reasonable basis been adopted to estimate these resource requirements?
Have factors such as potential increasing wages and staffs turnover
of information technology staff been taken into account in formulating
the project plan and resource requirements?
|
| 9. |
Has the institution established strong
monitoring of progress throughout the process to address the Year
2000 problem? Has a system been established for tracking utilised
resources (expenses, internal and external personnel, and technological
equipment)?
|
| 10. |
Have there been any significant changes
to established target dates? Do such changes materially affect the
ability of the institution and its subsidiaries and branches to
be ready in a timely manner?
|
| 11. |
Have there been any missed milestones?
If so, what were the reasons for the missed milestones and the effect
on the overall plan? |
Suggested documentary evidence that the Reviewer can ask for review:
- Detailed inventory of systems of the institution and its subsidiaries
and branches, with risk analysis and priorities assigned;
- Year 2000 detailed project plan for the institution
and its subsidiaries and branches;
- Resource requirements (including appropriately skilled personnel,
contractors, vendor support, budget allocations, and hardware capacity)
for the Year 2000 project;
- Procedures for monitoring the progress against schedules and the
utilised resources against budget; and
- Sign off procedures for key milestones.
Section IV - Modification
Objective of assessment:
The Reviewer should assess and report on whether the institution has
taken the necessary measures to ensure the systems that would be used
by the institution and its subsidiaries and branches, especially critical
systems, have been or would be properly modified.
General description of sound practices:
The additional resources needed for the project (e.g., additional hardware
equipment/capacity for modification and testing) should be acquired
or contracted. Systems needing fixing should be modified, upgraded,
replaced, outsourced or discontinued. For those systems that would not
be modified, upgraded, replaced, outsourced or discontinued, procedures
should be developed to handle the Year 2000 problem for such systems.
Execution should be done systematically with priorities set in accordance
with risk and critical systems should be modified first.
A clear understanding of what the vendor or service provider means
by being year 2000 compliant should be obtained. While a warranty or
certification may be sought or offered, the institution must recognise
the need for rigorous testing is not obviated by such a warranty or
certification.
There should be adequate controls over the modification (including
upgrade, replacement, outsourcing or discard) of systems. If third-party
contractors perform certain modification work, the institution should
maintain close monitoring of the quality and progress of the work of
the contractors.
Suggested questions that the Reviewer may ask:
| 1. |
Have additional resources needed for
the project been acquired or contracted?
|
| 2. |
Has the institution communicated date
format changes with external entities with which they exchange data?
|
| 3. |
Have procedures been developed to handle
the Year 2000 problem for those systems that cannot be modified,
upgraded, replaced, outsourced or discontinued?
|
| 4. |
Are modifications being done systematically
with priorities set in accordance with risk? Are critical systems
being modified first?
|
| 5. |
Have clear understandings of what the
vendor or service provider means by being year 2000 compliant been
obtained? Does the institution recognise that the need for rigorous
testing is not obviated by a warranty or certification?
|
| 6. |
Are there adequate controls over the
modification (including upgrade, replacement, outsourcing or discard)
of systems? In particular, are there change control procedures in
place to ensure modifications to systems are properly documented
and managed? If vendor technicians and outside consultants are engaged,
would they be subject to similar controls?
|
| 7. |
If third-party contractors perform certain
modification work, has the institution maintained close monitoring
of the quality and progress of the work of the contractors? Are
there formal engagement letters with the third-party contractors?
|
| 8. |
What are the natures of problems or issues
that have arisen during the course of modifications (for example,
resource shortages, backlogs, bottlenecks, and failures)? How have
these issues been addressed? |
Suggested documentary evidence that the Reviewer can ask for review:
- Sample of correspondence with vendors and service
providers;
- Engagement letters with third-party contractors;
- Control procedures related to modification work performed by third-party
contractors, if applicable; and
- Progress report related to the modifications of systems.
Section V - Testing
Objective of assessment:
The Reviewer should assess and report on whether the institution has
taken the necessary measures to ensure the systems that would be used
by the institution and its subsidiaries and branches, especially critical
systems, have been or would be properly tested for Year 2000 readiness.
General description of sound practices:
Systems should be tested according to priorities. In addition to testing
of individual modified systems including upgraded components, the interaction
of such systems with the institution's other systems with which they
interface directly should also be tested. The institution should also
conduct external testing with external entities with whom it exchanges
data electronically. As far as possible, "end-to-end" testing
should be conducted to verify the ability of the institution to originate
a transaction to transmit test data to a receiving entity or system
through an intermediary (e.g., financial systems provided by exchanges
or clearing houses).
If certain user groups test certain systems provided by vendors or
service providers, the institution should evaluate the applicability
of the user group test results to it before relying on the user groups
testing. Measures should be taken to manage the residual risks if the
test results of the user groups cannot be fully applicable to the institution.
For those systems that will not be tested, the institution should have
evaluated and determined that the relevant vendors and service providers
have successfully tested their systems. For those systems that will
not be modified, the procedures developed to handle the Year 2000 problem
of such systems should be tested.
Written test plans should be developed to describe how the testing
will be conducted. In general, test plans should include, at minimum,
the following elements: a description of testing environment, testing
methodology (e.g., test scripts, development of test data), testing
schedules, testing of relevant critical dates, documentation of test
results, the allocation of human and financial resources and requirements
for user participation.
End users of the systems should be involved in defining what should
be tested and the expected results, validating the actual testing results
against the expected results and signing off the systems. Appropriate
training on how the testing would be conducted should be provided to
personnel participating in the testing.
Proper control procedures should be established over the testing process.
In particular, there should be "clean management" procedures
to prevent contamination or corruption of operational systems and related
databases during and after testing process. Moreover, the status of
any problems identified during testing should be tracked closely to
ensure such problems will be fixed and re-tested accordingly. If third-party
consultants are engaged to conduct the testing, they should be subject
to similar controls. Moreover, their quality of work and progress should
be carefully monitored.
Suggested questions that the Reviewer may ask:
| 1. |
Is testing for systems conducted according
to priorities?
|
| 2. |
Does the testing include the validation
of the interaction of modified systems with the institution's other
systems with which they interface directly?
|
| 3. |
Does the institution have plans to conduct
external testing with external entities (e.g., exchanges, clearing
houses) with whom it exchanges data electronically? Does it have
plans to conduct "end-to-end" testing with service providers
(e.g., financial systems provided by exchanges or clearing houses)
as far as possible?
|
| 4. |
Would the applicability of the user groups
test results be evaluated before such results are relied upon? Would
there be measures to manage the residual risks if the test results
of the user groups cannot be fully applicable to the institution?
|
| 5. |
For those systems that would not be tested,
how would the institution evaluate and determine that the relevant
vendors and service providers have successfully tested their systems?
For those systems that would not be modified, have the procedures
developed to handle the Year 2000 problem of such systems been tested?
|
| 6. |
Have written test plans been developed
to describe how the testing would be conducted? Do the test plans
include, at minimum, the following elements: a description of testing
environment, testing methodology (e.g., test scripts, development
of test data), testing schedules, testing of relevant critical dates,
documentation of test results, the allocation of human and financial
resources and requirements for user participation?
|
| 7. |
Would the following critical dates, and
the rollover or progression before and after these dates, be generally
tested? If automated tools would be used to simulate these dates,
has the adequacy of the testing of the operating system been assessed?
|
|
Date
|
Reason
|
| April 9, 1999 |
9999 on the Julian Calendar. The
99th day of the year 1999. 9999 denotes the "end of input"
in many computer programs. |
| September 9, 1999 |
9999 on the Gregorian Calendar. 9999
denotes the "end of input" in many computer programs. |
| December 31, 1999 |
Last day in 1999 year. |
| January 1, 2000 |
Beginning of the Year 2000. |
| January 3, 2000 |
First business day in the Year 2000. |
| January 10, 2000 |
First date to require a 7-digit date
field (1/10/2000). |
| January 31, 2000 |
End of the first month of the year
2000. |
| February 29, 2000 |
Leap year day. |
| March 31, 2000 |
End of first quarter of 2000. |
| October 10, 2000 |
First date to require an 8-digit
date field (10/10/2000). |
| December 31, 2000 |
End of Year 2000. |
| January 1, 2001 |
Beginning of the Year 2001. |
| December 31, 2001 |
Check that year has 365 days. |
8. |
Have end users of the systems been involved in defining what should
be tested and the expected results, validating the actual testing
results against the expected results and signing off the systems?
Has appropriate training on how the testing would be conducted been
provided to personnel participating in the testing?
|
| 9. |
Have proper control procedures been established
over the testing process? In particular, are there "clean management"
procedures to prevent contamination or corruption of operational
systems and related databases during and after testing process?
Are there procedures in place to closely track status of any problems
identified during testing to ensure all problems identified during
testing would be fixed and re-tested accordingly? If third-party
consultants are engaged to conduct the testing, would they be subject
to similar controls? Moreover, would their quality of work and progress
be carefully monitored?
|
| 10. |
What are the natures of problems or issues
that have arisen during the course of testing (for example, resource
shortages, backlogs, bottlenecks, and failures)? How have these
issues been addressed? |
Suggested documentary evidence that the Reviewer can ask for review:
- Control policies and procedures over the Year 2000 testing process;
- Sample of Year 2000 test plan for critical systems, including internal
integration testing and external testing (if applicable);
- Sample of documentation of Year 2000 test results and user sign-off
for critical systems, in particular internal integration testing and
external testing (if applicable); and
- Progress report related to testing.
Section VI - Implementing Tested, Compliant Systems
Objective of assessment:
The Reviewer should assess and report on whether the institution has
taken the necessary measures to ensure the systems that would be used
by the institution and its subsidiaries and branches, especially critical
systems, have been or would be properly implemented in production.
General description of sound practices:
Putting tested, compliant systems into production (including data conversion)
well before the end of 1999 should be an objective for the institution
because it allows counterparties and customers to interact with the
systems during normal day-to-day activities. Additionally, once back
in production, normal maintenance of the application using standard
change-control procedures becomes possible.
In some instances, the institution may choose to implement modified
systems after rigorous testing of functionality but before completing
Year 2000 testing, especially external testing. While this approach
has the advantage of minimising the length of time a particular application
is "frozen" from normal maintenance and change-control procedures,
it does not lessen the need for thorough Year 2000 testing.
Appropriate re-testing of systems in production should be addressed
when other Year 2000 applications are introduced. Frequently, compliant
systems become non-compliant because file formats or other components
change in another application with which there is interaction.
Procedure manuals should be written or rewritten and disseminated.
Training programs should be provided, and help desks established or
retrained.
Suggested questions that the Reviewer may ask:
| 1. |
Are tested systems put into production
(including data conversion) as soon as practical to allow counterparties
and customers to identify and resolve any difficulties they may
have in interacting with the application?
|
| 2. |
Does the institution have sound procedures
in place to control version changes in applications? Are these procedures
followed rigorously with respect to Year 2000 implementation?
|
| 3. |
After a tested application has been put
into production, are there adequate plans in place to re-test the
application when other applications with which it interacts are
changed?
|
| 4. |
Has the institution implemented revised
operation procedures for the new or corrected applications and tested
them?
|
| 5. |
Has the institution trained all users
and operators for the new or corrected applications, as well as
latest releases of third-party software?
|
| 6. |
Has the institution established help
desks to provide support to users on using the implemented systems? |
Suggested documentary evidence that the Reviewer can ask for review:
- Implementation schedule of all modified systems;
- Sample of implementation (including data conversion) plans of critical
systems;
- Sample of documentation of implementation (including data conversion)
results;
- Operating procedures manuals;
- Training plan and material; and
- Progress report related to implementation.
Section VII - Contingency Planning
Objective of assessment:
The Reviewer should assess and report on whether the institution has
taken the necessary measures to ensure contingency plans have been or
would be properly developed and tested to ensure business continuity
of the institution and its subsidiaries and branches and to deal with
other Year 2000 problems that may arise.
General description of sound practices:
The need to develop contingency plans to assure business continuity
is an integral part of the Year 2000 project. Some elements of contingency
plans, such as the identification of alternatives for external dependencies
and specific dates for making decisions on whether to change vendors,
should be done as part of the assessment phase as inventories are developed.
Other elements such as specific plans for business resumption can be
done more effectively when the likelihood of particular events occurring
is better understood. Because this understanding is developed most effectively
as testing begins, especially external testing, efficient use of resources
suggests that contingency planning in this area will be a priority during
the testing process. In particular, it might be necessary to develop
contingency plans to ensure that customers' assets are protected and
that their instructions can be effected after the 1 January 2000.
Some contingency plans can be developed only in cooperation with counterparties,
customers, and the public sector. In particular, areas of systemic concern
need to have coordinated planning efforts because developing sound approaches
will require knowing what approaches others are using.
Finally, the institution should also develop contingency plans related
to its general functioning. This would include, inter alia,
anticipating expected losses caused by the Year 2000, planning for counterparties
being unable to perform, anticipating above average use of credit lines
or cash withdrawals, and planning limitations on business activities
that are highly dependent on technology (for example, trading activities).
Suggested questions that the Reviewer may ask:
| 1. |
Does the institution have contingency
plans to deal with slippage in the Year 2000 modification, testing
or implementation phases, and with a situation where the delivery
date of any critical system cannot be met or, if the modified systems
do not perform as planned?
|
| 2. |
Does the institution have a contingency
planning process in place to ensure that operations can continue
if some systems do not function properly as of 1 January 2000? Does
this process take into account both the risks associated with a
particular activity and the likelihood of particular events occurring?
|
| 3. |
Does the institution have estimates of
how long they can operate under various contingency plans?
|
| 4. |
Are there any significant critical systems
that will not meet the deadline for Year 2000 compliance? Is senior
management addressing these problems?
|
| 5. |
Do the contingency plans deal with equipment
with embedded chips (e.g., security systems, vault, fire systems)
and infrastructure issues (e.g., telecommunications, electrical
power and water)?
|
| 6. |
Do the contingency plans identify adequate
levels of responsibility and readily available resources (internal
and external) to deal with any problems encountered with the millennium
date change? Has the institution prepared disaster recovery teams
to deal with multiple system failures and tested the use of manual
record keeping?
|
| 7. |
Has the institution considered the impact
on customers of various contingencies and how negative consequences
can be mitigated? Are mechanisms in place for a fair and expeditious
resolution of disputes with customers that may arise?
|
| 8. |
Has the institution developed contingency
plans related to its general functioning? Do the contingency plans
deal with potential liquidity, market, credit, and legal risk issues?
Has the institution planned for higher than normal cash withdrawals
by customers ahead of 31 December 1999?
|
| 9. |
Have the contingency plans and their
revisions been tested? Are the contingency plans being updated with
issues / problems encountered? |
Suggested documentary evidence that the Reviewer can ask for review:
- Contingency plans; and
- Progress report related to development and testing of contingency
plans.
Section VIII - assessing and managing Counterparty risks
Objective of assessment:
The Reviewer should assess and report on whether the institution has
taken the necessary measures to ensure the Year 2000 issue-related risks
arising from the business counterparties of the institution and its
subsidiaries and branches have been or would be properly assessed and
managed.
General description of sound practices:
Because business counterparties (e.g., correspondents and customers)
are also subject to the Year 2000 issue, they too must make the necessary
changes to conduct business normally. Testing normal connectivity and
message transfers with business counterparties is essential but not
enough. If they have not also made the necessary adjustments to their
own systems, they could pose credit and liquidity risks to the bank.
The institution and its subsidiaries and branches should develop a
due diligence process to assess and manage their Year 2000 issue-related
risks arising from business counterparties. Credit officers need to
understand the Year 2000 risks faced by their business counterparties
and how well their business counterparties are managing these risks.
Current financial performance will not be an indication of future performance
for organisations that have not developed sound plans and provided for
appropriate resources to carry them out.
Suggested questions that the Reviewer may ask:
| 1. |
Is there any arrangement to assess the
Year 2000 preparedness of business counterparties? Has the institution
discussed the Year 2000 problem with its major customers and business
counterparties and assessed whether they will be able to meet their
financial and informational obligations to the institution?
|
| 2. |
Has Year 2000 readiness been incorporated
into the list of criteria for assessing the suitability of customers
and business counterparties? Has Year 2000 preparedness been incorporated
as one of the standing items in their credit proposal and ongoing
credit monitoring process for their customers?
|
| 3. |
Has the institution amended policies
and business procedures (such as credit, mergers/acquisitions, and
investment banking) to incorporate consideration of Year 2000 risk
in dealing with business counterparties? |
Suggested documentary evidence that the Reviewer can ask for review:
- Revised policies and procedures for assessing and managing Year
2000 issue-related risks arising from business counterparties.
Section IX - overall assessment
The Reviewer should also assess and report on whether the progress
of Year 2000 preparations of the institution and its subsidiaries and
overseas branches is behind, ahead or on schedule according to the project
plan.
The Reviewer should report on whether he has identified any major concerns
or weaknesses in the institution's Year 2000 preparations in the course
of the assessment, including those which might affect the ability of
the institution to meet the deadlines established by the HKMA.
The Reviewer should recommend additional actions that may assist the
senior management of the institution to address the problem areas.
Updated on 10 Aug 1998
|